Ningbo C.S.I. Fifth-stage factory relocation work successfully carried out

Pubtime:2016-09-15

      From September 3rd, Ningbo C.S.I. Fifth-stage factory started to relocate, first-stage seven large-scale equipment started moving to new plants successively, under close cooperation with each department in company, up to September 28th, first large-scale equipment “Grinder MK82160” had been successfully installed, and entered accessory testing stage, formal operation condition was completely contained.

      During national day, company related departments arranged overtime work personnel reasonably, other equipment started installation successively and follow-up work step-by-step carried out. According to our plan, main equipment relocation work shall be finished before the end of the year.